Titre : Sidi Said Dam (Morocco)

Pays : Maroc

Organisme Financement : Kuwait Fund for Arab Economic Development

Date : 24-04-200
Expected Completion Date : 12-2008

Implementing Agency : MINISTRY OF EQUIPMENT

Project Objectives
THE PROJECT AIMS TO IMPROVE THE IRRIGATION SYSTEM OF THE LOW AND MIDDLE MOULOUYA AREA, EQUPIED AT ABOUT 72,000 HA. TO PROTECT MOHAMMED V DAM AND HAMADIPROJECT, AND THE AREA DOWNSTREAM FROM THE DAM AGAINST FLOODS AND SILTING-UP.

Project Description
THE PROJECT CONSIST OF CONSTRUCTION OF REINFORCE COMPACTED CONCRETE DAM ON MOULOUYA RIVER WITH A CAPACITY OF ABOUT 400 MILLION M3. IT INCLUDES PREPARATION WORKS AND MECHANICAL WORKS FOR THE DAM, AND CONSULTING SERVICES FOR DESIGN AND SUPERVISION OF THE DAM.

Estimated Project Cost : 14,182,769 KD
Kuwait Fund Financing : Loan 14,182,769 KD
Mars 2011 : 1 KD = US$3.40