Samendeni Valley Integrated Development Project (Burkina Faso)

Burkina Faso

THE OPEC FUND FOR INTERNATIONAL DEVELOPMENT

Pays : Burkina Faso

Secteur Agriculture & Agro-Industry

Date d’approbation : 3/13/2007

Loan Administrator : Kuwait Fund For Arab Economic Development (KFAED)

Agence d’exécution : Ministry of Agriculture, Hydraulics and Fisheries

Co-financeurs : ISDB, KFAED, BOAD, SFD, OFID, Government, BADEA, ABUDF, FRDC, MCC Grant, Turk Eximbank

Contexte

Although Burkina Faso possesses ample agricultural land, erratic rainfall and frequent drought hinder crop yields and thus threaten food security. In order to enable water resources to be stored more effectively, the project will construct a dam in the Samendeni Valley in western Burkina Faso in Houet Province, home to some 900,000 inhabitants.

Description
The earth dam will be built on the Mohon River and have a storage capacity of 1,050 million m3. Other works include construction of a 2.6 MW hydropower plant and 23 km-long transmission line, as well as diversion structures for irrigating 1,500 ha of land for cultivation. Potable water facilities will also be built in the nearly city of Bobo-Dioulasso.

Informations financières
Financement OPEC : US$7,000,000
Total projet : US$180 million