Basrah Water Supply Improvement Project (Iraq)

Irak

Titre : Basrah Water Supply Improvement Project (Iraq)

Country : The Republic of Iraq

Target Area : Basrah City and Hartha City, Basrah Governorate

Loan Agreement : June 11, 2008

Schedule : July 2008–November 2014 (77 months).

Borrower : The Government of the Republic of Iraq
Executing Agency : Basrah City and Hartha City, Basrah Governorate

Project Objective
The objective of the project is to improve quantity and quality of the water supply situation in the cities of Basrah and Hartha, Basrah Governorate in southern Iraq, by rehabilitating and newly constructing water treatment plants, as well as by improving of distribution networks and other facilities ; thereby contributing to the economic and social reconstruction of the two cities.

Loan Amount : 42,969 million yen ;

JICA (Japan International Cooperation Agency)

Page publiée le 26 août 2012, mise à jour le 17 juin 2019